|
WESTON Performs Causeway Remediation and
Coastal Restoration for the U.S. Army Corps of Engineers New England
District
Stratford Army Engine Plant, Stratford,
CT
Located within the Housatonic River Estuary,
the 124-acre Stratford Army Engine Plant was closed under the Base
Realignment and Closure program and earmarked for potential transfer
to the Town of Stratford, Connecticut. A man-made causeway, which
formerly allowed facility access by seaplane, extends 800 feet into
the mudflats of the Housatonic River. Environmental investigations
of the causeway materials indicated volatile organic compound contamination
and the potential for erosion and deposition of contaminants in adjacent
sensitive ecosystems. WESTON conducted
a targeted excavation of contaminated soils, installed an innovative
cover system to prevent erosion of and direct contact with underlying
soils, and restored the property for reuse as public recreational
space.
“WESTON provided
valuable feedback through constructability reviews, offered time
and budget saving recommendations with regard to operations and
monitoring, and aggressively resolved quality control issues that
had potential to extend project cost and schedule.”
—Michelle
Clemens, Engineering Manager, Army Corps of Engineers
WESTON Meets Site Challenges
Concerns over potential geophysical instability of the causeway prompted
WESTON to implement a construction approach that minimized stress on
the underlying materials while meeting an aggressive schedule.
Because of potential negative impacts of
sedimentation on sensitive oyster beds adjacent to the project area,
state regulations prohibited work below the high-tide mark between
April and September. Restricted to a 6-month construction window during
the winter months, WESTON successfully installed cover system components
within the tidal zone. Potential geophysical instability required
frequent monitoring of the causeway surface elevation for settlement.
WESTON’s construction approach allowed work to
continue without interruption, enabling the team to meet regulatory,
environmental, and engineering requirements.
Working on a highly secure government facility, WESTON carefully planned
and executed an aggressive schedule with no reportable lost days due
to injury or accidents.
Site Challenges
-
Performed abatement and demolition to improve future access
to the causeway
-
Performed work during nonstandard hours to accommodate a
tidally influenced project area
-
Completed construction on schedule despite low-tide windows
as short as 2 hours
-
Minimized potential impacts on sensitive ecological receptors
-
Stabilized man-made causeway and installed protective cover
system
Innovation and Value Engineering
Operating under strict environmental regulations and engineering specifications,
WESTON implemented a range of site-specific value-added solutions:
WESTON excavated contaminated soil for off-site disposal and demolished
two asbestos-contaminated buildings to improve access to the causeway.
WESTON graded and contoured the causeway surface and installed a dual-component
engineered cover system to prevent direct contact between sensitive
ecological receptors and the remaining underlying contaminated soil.
WESTON conducted a geotechnical analysis to determine maximum allowable
point loads on the potentially unstable causeway surface. WESTON deployed
smaller, more maneuverable equipment and reduced the size of individual
cap components to avoid exceeding point load constraints and increase
safety during construction.
The lower cover system consisted of rock-filled polymeric marine mattresses
and was installed along the causeway within the tidal zone to stabilize
contaminated materials and prevent erosion. The second component consisted
of sand bedding and interlocking concrete blocks installed along the
top surface of the causeway to stabilize underlying materials and prevent
direct contact by human or ecological receptors. For both components,
this project constituted an innovative application. WESTON worked closely
with the design engineer and product manufacturers to meet stringent
design tolerances and project-specific quality control requirements.
Project Stakeholders
WESTON communicated regularly with numerous project stakeholders, including
the client representatives and regulatory agencies. Because restoration
required two distinct design plans, WESTON encouraged partnering sessions
to dovetail design plan implementation and resolve construction issues,
therefore limiting delays, ensuring a high-quality product, and restoring
an environmentally sensitive coastal area.
Future Goal: Reuse as a Town Park
-
Innovative cap design ensured structural stability in an
environmentally sensitive estuary
-
WESTON partnered with critical stakeholders and maintained
communication with local, state, and federal constituents to
ensure a team-based approach and drive project completion
-
WESTON completed work within an aggressive cold-weather schedule
-
All project phases supported the ultimate goal for the site:
The beneficial reuse of the causeway as a public park
-
Incorporated Town of Stratford design elements into surface construction
to provide subsurface utilities necessary for use
|